What Belongs in a Remodeling Contract in California

A remodeling contract in California is more than a price and a signature. It says what will be built, how it will be built, when you pay and what happens when plans change. A clear contract protects you and the contractor alike.

California has specific rules for home improvement contracts. Some items must be in writing, some notices must be included and some limits apply to how much you pay up front. Knowing them helps you read a contract with confidence.

Below, we cover what a contract should include and the questions to ask before you sign. This is general information, not legal advice.

Key takeaways

  • California requires a written contract for home improvement projects over $500.
  • The contract should describe the work, materials, payment schedule, permits and approximate start and completion dates.
  • Since 2026, the contract must say whether subcontractors will be used.
  • For most contracts, the down payment can’t be more than $1,000 or 10 percent of the price, whichever is less.
  • Progress payments should not get ahead of the work done.
  • Any change to the price or scope should be a written change order, signed before the change.
  • Most homeowners who sign at home have three business days to cancel. Homeowners 65 or older have five.

Why a written remodeling contract matters

A remodel involves dozens of decisions, from cabinet styles and tile sizes to who pulls the permit. When those details live only in conversations, memories can differ months later. A written contract puts them in one place.

The Contractors State License Board (CSLB) calls a written agreement one of the most important communication tools for both the contractor and the consumer.

The CSLB also explains that California requires a written contract for home improvement projects over $500. That rule comes from Business and Professions Code section 7159. The contract and any changes must be in writing, legible and easy to understand.

What the scope of work should include

The scope of work is the heart of the contract. It describes what will be done, in enough detail that two people would read it the same way.

A detailed description of the work

The CSLB says the contract should describe the products to be used and how the work will be performed. That can include sizes, colors, who will do which part of the work, the amounts of materials and model numbers.

For a kitchen, that may mean the cabinet line and finish, the countertop material and edge, and the sink and faucet. It should also say which appliances you supply and which the contractor supplies. For a bathroom, it may mean the shower size, tile, glass, valve and vanity.

If a contractor promised something out loud, ask for it in writing. The CSLB advises putting every verbal promise into the contract.

What is not included

A good scope also lists what is not included. Painting outside the work area, moving furniture, appliance hookups or patching other rooms are common gray areas. Writing them down helps everyone avoid a misunderstanding later.

Allowances

An allowance is a set amount in the contract for an item you have not chosen yet, such as tile or light fixtures. If you pick something that costs more or less, the price adjusts. Ask which items are allowances and how adjustments are handled.

Allowances are useful when you need more time to choose, but they carry risk if the amount is set too low. Visiting a showroom before you sign can help you judge whether they fit your taste.

Curious what a project like this would cost? Try our kitchen or bathroom cost calculator, or call (916) 776-5762 to talk it through.

Cleanup and debris

The CSLB suggests the contract include details such as cleanup and removal of debris and materials. Daily cleanup, dust protection and final cleaning are worth spelling out.

What the payment terms should say

Payment terms are where many disputes start. California rules give homeowners important protections here.

Down payment limits

For most home improvement contracts, the down payment cannot be more than $1,000 or 10 percent of the contract price, whichever is less. That cap is set by Business and Professions Code section 7159.5. The CSLB notes there are no exceptions for special-order materials.

The one rare exception is for contractors who carry a blanket performance and payment bond approved by the CSLB. According to the CSLB contract guide, this bond is what allows a larger down payment. The same bond also exempts the contractor from some progress payment rules and the Mechanics Lien Warning.

A written payment schedule

The contract must include a detailed, written payment schedule. The CSLB explains that payments to the contractor cannot exceed the value of the work performed or materials delivered, except for the down payment.

A clear schedule ties each payment to a stage of work. Examples include demolition, rough-in inspections and cabinet installation. Rough-in is the stage when new plumbing and wiring run through the open walls before drywall goes up.

Tying payments to stages means you pay as the work moves forward. The last payment usually follows the final walkthrough.

Financing

If you plan to finance the project, the payment schedule and your loan payouts should line up. Ask your lender how and when funds are released. If you’d like to explore it, financing options are available.

How change orders should work

Plans change during almost every remodel. You may choose a different tile, or the contractor may find rot behind a wall. The contract should say how changes are handled.

Written and signed before the change

The CSLB says that if the contract price or scope of work needs to change, it must be done with a written change order. Both you and the contractor sign it before the change, and it becomes part of the contract.

A clear change order describes the new work, any change in price and any change in schedule. It should be specific enough that you know exactly what you are approving.

Hidden conditions

Older homes often hide problems behind walls and under floors. Ask how the contract handles conditions that no one could see before work started. Our Victorian bathroom remodel in Sierra Oaks shows what working in an older home can involve.

Who handles permits and inspections

The CSLB says the contract needs written direction about who will get the necessary permits. In most remodels, the contractor pulls the permits, but the contract should say so clearly.

The CSLB’s homeowner checklist also suggests asking whether permit fees are included. It’s worth asking how inspections will be scheduled too. Our posts on kitchen remodel permits and bathroom remodel permits in Sacramento cover the basics.

What the schedule section should say

A California home improvement contract lists an approximate start date and an approximate completion date. It also describes what counts as the start of work, which the CSLB’s sample home improvement contract calls “substantial commencement.”

Start and completion dates are estimates, but they should be clearly documented. The contract should explain how delays are communicated and how approved changes may affect the schedule. Weather, inspections, material lead times and hidden conditions can all play a part.

What the contract should say about the contractor

The CSLB says the contract should identify the contractor, the business address and the contractor license number. You can look up any license on the CSLB Check A License page before you sign.

Since January 1, 2026, a home improvement contract must also say whether subcontractors will be used on your project. If they will, you can ask for a list with each subcontractor’s name, contact information, license number and classification. The CSLB covers this change in its summary of new laws for 2026.

If a salesperson signs the contract for the company, they must be registered with the CSLB as a home improvement salesperson. For more on why licensing matters, see our post on why you should not hire unlicensed contractors.

What notices must be included

California home improvement contracts include several required notices. They can look like fine print, but they matter.

Your right to cancel

If you sign a home improvement contract at home, you usually have three business days to cancel. The CSLB’s guide for seniors explains that homeowners 65 or older have five business days. It also advises not letting the contractor begin work or pull permits during that period.

In a declared disaster area, homeowners have seven business days to cancel a contract to repair or rebuild a damaged home. To cancel, you only need to give the contractor written notice. The CSLB contract guide says the contractor must then return your money within 10 days.

Since January 1, 2026, a home improvement contract must also include the contractor’s email address and a phone number to help you find and complete the Notice of Cancellation. You can cancel a qualifying contract by email, too. The CSLB lists this change, from AB 1327, in its 2026 new laws bulletin.

The right to cancel does not apply to contracts signed at the contractor’s place of business. The CSLB sample contract shows how each cancellation notice is written and how to use it.

Mechanics lien warning

A mechanics lien is a claim against your property. Someone who worked on or supplied the project and was not paid can file one, even if you paid your contractor. That’s why most California home improvement contracts must include a Mechanics Lien Warning, which the CSLB checklist also calls a Notice to Owner.

The CSLB explains how to prevent a mechanics lien. One key step is a lien release, which is a signed form that gives up the right to file a lien for a payment. Ask how lien releases will be handled each time you pay.

Other notices

The sample contract shows other notices, such as information about the contractor’s insurance and your right to request a performance and payment bond. Read each one and ask questions about anything you do not understand.

Getting warranties in writing

The CSLB suggests getting any warranty for labor and materials in writing. That includes the contractor’s own warranty and any manufacturer warranties.

At Luxehome Construction, we offer a full one-year labor warranty on every project, and each customer receives a Warranty Certificate showing the expiration date. Manufacturer warranties on products are separate and come from the manufacturer.

Other details that belong in the contract

A few practical details aren’t always in a standard form, but they make day-to-day work easier.

Materials and substitutions

Sometimes a product is back-ordered or discontinued. The contract can say how substitutions are handled. A simple rule is that no substitution happens without your written approval, and any price change goes on a change order.

Who orders what

Some homeowners buy their own fixtures or appliances. If you plan to supply items, the contract should say which ones, when they need to be on site and who is responsible if an item arrives damaged. Mixing owner-supplied and contractor-supplied items without clear notes is a common source of confusion.

Site access and house rules

You will have a crew working in your home while your family lives there. A written project plan can cover working hours, which entrance the crew uses and where tools and materials are stored. It can also cover bathroom access and how pets are handled.

Dust protection and communication

Ask how the work area will be sealed off and how floors outside it will be protected. Also ask who your main contact is and how often you will get updates. Writing these into the plan sets clear expectations from day one.

How the contract should handle the end of the project

The last stage of a remodel deserves as much attention as the first.

Final walkthrough and punch list

A final walkthrough is a review of the finished work with the contractor. Small items that need attention go on a punch list. The contract can tie the final payment to completing that list.

Final payment and lien releases

Before you make the final payment, ask for lien releases from the contractor and from subcontractors and suppliers who worked on the job. The CSLB posts the state’s lien release forms online.

Closing out permits

Make sure every permit has a final inspection and is closed out. An open permit can cause trouble when you sell or refinance. Ask for copies of the final inspection records.

If there is a disagreement

Even with a clear contract, questions come up, and most are settled by talking through what the contract says. Some contracts also include a clause on how disputes are resolved, such as mediation or arbitration. Read that section closely and ask about anything you do not understand before you sign.

How Sacramento projects shape the contract

California rules apply statewide, but local conditions affect what goes into the scope.

Older homes

Many homes in East Sacramento, Land Park and Curtis Park are decades old. Contracts for these homes often need clear language about testing for lead paint or asbestos and about hidden conditions.

Raised foundations with crawl spaces can also reveal old pipes or pest damage once work begins. The contract should explain how those finds are priced and approved.

Different building departments

The City of Sacramento, Sacramento County and cities such as Rancho Cordova, Folsom, Elk Grove and Roseville each run their own building departments. The permit section should name the right agency for your address.

How to compare contracts from different contractors

If you get more than one bid, line the contracts up section by section. Check that each scope covers the same work and materials, and that the allowances are realistic for your choices. A lower bid with a thin scope may leave more to change orders later.

What to check before you sign

Use this list before you sign:

  • Is every promise you heard written into the contract?
  • Does the scope describe the work, materials and model numbers in detail?
  • Is the down payment within the state limit, and is there a written payment schedule tied to the work?
  • Does the contract say who gets permits and when work will start and end?
  • Does it explain how change orders and hidden conditions are handled?
  • Does it list the contractor’s name, address and license number?
  • Did you receive the right-to-cancel notice and the Mechanics Lien Warning?
  • Is the warranty in writing?

If the contract is signed on a tablet or laptop, the CSLB’s guide for seniors suggests asking for an immediate paper copy.

How we handle contracts at Luxehome Construction

Our process starts with a free consultation, then design and planning with 3D design previews, then selections and scope. By the time you see a contract, we’ve talked through the finishes, fixtures and functional details, so the scope reflects what you chose.

During construction, we cover floors with drop cloths and cardboard, hang plastic dust barriers, clean up daily and keep you updated along the way. You have direct access to Alex, our owner and general contractor. At the end, we do a final walkthrough of finishes, fixtures and function with you before the project is complete.

Common questions

Do I need a written contract for a small remodel?

California requires one for home improvement projects over $500. Even below that amount, putting the details in writing is a good idea.

Can I find out who the subcontractors are?

Yes. If subcontractors will work on your project, you can ask your contractor for a list with their names, contact information, license numbers and classifications.

What should I keep after the project is done?

Keep the signed contract, every change order, lien releases, payment records, final inspection records and warranty paperwork together. They help if you sell, refinance or have a warranty question later.

Signing with confidence

A good remodeling contract is detailed, clear and fair to both sides. Take your time, ask questions and keep a signed copy.

Luxehome Construction is licensed, bonded and insured (CSLB #1104114) and has served the Greater Sacramento area since 2018. We’re glad to walk you through our process and contract for your home renovation. Call (916) 776-5762 or request a free consultation.